Ninh Binh - Hai Phong expressway enters the simultaneous construction phase

Mai Hương |

Hung Yen - Vice Chairman of Hung Yen and Ninh Binh Provincial People's Committees inspects the progress and site clearance of the Ninh Binh - Hai Phong expressway project section passing through Ninh Binh.

On January 29, Vice Chairman of Hung Yen Provincial People's Committee Lai Van Hoan and Vice Chairman of Ninh Binh Provincial People's Committee Nguyen Cao Son inspected the progress of the Ninh Binh - Hai Phong expressway project (CT.08), the section passing through Ninh Binh province.

At the inspection, representatives of the project enterprise reported on the overall implementation situation. Up to now, the appraisal and approval of technical design documents and estimates have been completed for all 14/14 construction packages. Some construction drawing design items have been approved in a timely manner, meeting the requirements for implementation at the construction site.

For items that need adjustment, Hung Yen Provincial People's Committee has approved the policy of adjusting the design of 3 bridges on the route; currently, the project enterprise is completing appraisal procedures according to regulations.

The contractor selection work is basically completed, consulting, non-consulting and construction packages have been signed contracts, ensuring sufficient conditions to organize construction according to project progress. At the construction site, bomb and mine clearance, terrain survey, geology, and hydrology packages have been completed; construction packages are being deployed simultaneously.

Lãnh đạo hai tỉnh kiểm tra thực địa dự án cao tốc Ninh Bình – Hải Phòng
Leaders of the two provinces inspect the Ninh Binh - Hai Phong expressway project on the ground. Photo: Hung Yen Provincial e-Portal

As of January 22, 2026, the production value of the entire project reached about 525 billion VND, of which the section through Ninh Binh province reached 275 billion VND. For bidding packages in Ninh Binh province alone, hundreds of machines and equipment are currently mobilized along with more than 250 engineers and workers, organizing parallel construction for both road and bridge items.

Site clearance work has achieved many positive results, with about 95% of the route length handed over to contractors. Many bidding packages have 100% clean site for construction. However, there are still some obstacles related to residential land and technical infrastructure that localities need to continue to focus on removing.

After actual inspection in the Ninh Co river overpass area, the two Vice Chairmen of the Provincial People's Committee requested relevant departments, branches, and localities to closely coordinate with the project enterprise, accelerate site clearance, and strive to hand over the entire remaining site by mid-February 2026.

At the same time, requesting the project enterprise to urgently complete the material mine procedures, focus manpower and equipment, organize scientific construction, ensure progress, quality, safety and project efficiency in accordance with the direction of the Government and the Prime Minister.

Mai Hương
관련 뉴스

호치민시에서 카인호아로 가는 고속도로에서 타이어 폭발 위험 경고

|

카인호아 - 기능 기관은 연말에 이동 수요가 증가하여 타이어 파열 위험을 포함한 많은 교통 사고 위험이 잠재되어 있다고 경고합니다.

호치민시를 통과하는 비엔호아 - 붕따우 고속도로 구간 곧 완공 예정

|

호치민시 - 호치민시를 통과하는 비엔호아 - 붕따우 고속도로 구간은 98% 시공되었으며, 운영을 시작하기 위한 마지막 단계를 완료하고 있습니다.

응우옌탄빈 대령, 인민공안신문 편집장으로 임명

|

응우옌탄빈 대령 - 인민 공안 홍보국 부국장 - 은 인민 공안 신문 편집장으로 임명되었습니다.

우크라이나, 유럽에 무기 수출 센터 10곳 배치

|

우크라이나는 독일에 10개의 무기 수출 및 UAV 생산 센터를 열 예정이며, 이는 전시 전략의 큰 전환점을 의미합니다.

하노이 5층 건물 화재, 경찰이 갇힌 많은 사람들을 구조

|

하노이 - 동아잉의 사업 겸 주택에서 밤에 화재가 발생하여 기능 부대가 신속하게 현장에 도착하여 갇힌 많은 사람들을 제때 구조했습니다.

호치민시 교사 채용: 오늘 입학 서류 제출 마감일

|

호치민시 - 추가 교사 채용 서류 접수 마감일은 오늘(2월 9일) 오후 5시입니다.

베트남 여성 억만장자 3명과 증권 거래소 자산

|

포브스가 발표한 세계 억만장자 목록에는 빈그룹 대표 2명과 비엣젯 항공 대표 1명을 포함하여 베트남 여성 억만장자 3명이 포함되어 있습니다.

다낭 한강변에서 불이 켜진 4-0 말 마스코트

|

다낭 - 현대적인 기술 스타일의 "금마 4.0" 마스코트가 한강 강둑에 설치되어 올해 설날에 눈에 띄는 체크인 장소가 될 것으로 기대됩니다.

호치민시에서 카인호아로 가는 고속도로에서 타이어 폭발 위험 경고

Bình Quý |

카인호아 - 기능 기관은 연말에 이동 수요가 증가하여 타이어 파열 위험을 포함한 많은 교통 사고 위험이 잠재되어 있다고 경고합니다.

호치민시를 통과하는 비엔호아 - 붕따우 고속도로 구간 곧 완공 예정

Thành An |

호치민시 - 호치민시를 통과하는 비엔호아 - 붕따우 고속도로 구간은 98% 시공되었으며, 운영을 시작하기 위한 마지막 단계를 완료하고 있습니다.

Khắc phục hàng rào cao tốc bị cắt mở, ngăn nạn thả rông bò vào cao tốc

Duy Tuấn |

Lâm Đồng - Sau phản ánh về việc hàng rào cao tốc Vĩnh Hảo - Phan Thiết bị cắt mở, chăn thả bò sát mép đường, các đơn vị đã khắc phục và tuyên truyền.